No. | Owner & General Contractor | Project Name | Construction time |
1 | Chengdu Electrometallurgy Factory | Plants and Devices Anti-corrosion Project (Copper、Nickel and Cobalt Electrolysis) | 1996 |
2 | Panxi Tombarthite Co.,Ltd. | Plants、Devices and Sewage Treatment System Anti-corrosion Project | 1996 |
3 | Sichuan Resin Factory | 80,000 Tons / Year PVC、70,000 Tons / Year Caustic Soda Anti-corrosion Project | 1996 |
4 | FAW (Sichuan) Special Cars Co.,Ltd. | Surface Treatment Workshop、Electrophoresis Line Anti-corrosion Project | 1997 |
5 | Chengdu Iron Tower Plant | Pickling Workshop Anti-corrosion Project | 1997 |
6 | Sichuan Delong Tombarthite Co.,Ltd. | Plants、Devices and Sewage Treatment System Anti-corrosion Project | 1997 |
7 | Sichuan Shuangliu Non-ferrous Metal Smelting Co.,Ltd. | Electrobath and Tanks Anti-corrosion Project(Copper、Bluestone) | 1998 |
8 | Sichuan Chemical Industry Group | Hydrogen peroxide Program Anti-corrosion Project | 1998 |
9 | Sichuan Tianhua Co.,Ltd. | 300,000 Tons/ Year Synthetic Ammonia、520,000 Tons/ Year Urea Devices Anti-corrosion Project | 1993~1998 |
10 | Sichuan Tianhua Co.,Ltd. | Large Chemical Fertilizer Units、Natural Gas Pipelines and Prilling Towers Anti-corrosion Project | 1998 |
11 | Yibin Tianyuan Chemical Factory | 60,000 Tons / Year PVC、80,000 Tons / Year Caustic Soda Anti-corrosion Project | 1998 |
12 | Shifang Yingfeng Group | 100Kt/a Sulfur-based Compound Fertilizer、100Kt/a Sulfuric Acid Program Anti-corrosion Project | 1999 |
13 | Sichuan Chemical Industry Group | 200,000 Tons/ Year Synthetic Ammonia Program Anti-corrosion Project | 1990~1999 |
14 | Lutianhua Group Co.,Ltd. | 200,000 Tons/ Year Synthetic Ammonia、320,000 Tons/ Year Urea Devices Anti-corrosion Project | 1990~1999 |
15 | Sichuan Leshan Fangzhou Aluminum Co.,Ltd. | Electrophoresis tank and Sewage Treatment System Anti-corrosion Project | 1999 |
16 | Inner Mongolia Haiji Chemical Co.,Ltd. | 60,000 Tons / Year Caustic Soda、60,000 Tons / Year Chloroethylene and PVC Program Anti-corrosion and Insulation Project | 2000 |
17 | Inner Mongolia Haiji Chemical Co.,Ltd. | Calcium carbide、Utilities and Underground Pipe System Anti-corrosion Project | 2000 |
18 | Nuclear Industry Department Torch Chemical Industry Factory | Underground Pipe System、Sewage Treatment Device and 652 Main Device Anti-corrosion & Insulation Project(801 Project) | 2000 |
19 | Zigong Fuyuan Chemical Industry Co.,Ltd. | 40,000 Tons / Year United Alkali Anti-corrosion & Insulation Project | 2000 |
20 | Yibin Siliya Group Co.,Ltd. | PPV Anti-corrosion & Insulation Project | 2000 |
21 | Nanchong Oil Refinery | Pipe Anti-corrosion Project | 2000 |
22 | Wuliangye Group Co.,Ltd. | PBT Anti-corrosion Project | 2001 |
23 | Nuclear Industry Department Torch Chemical Industry Factory | 652 Main Device Metallic Thermospray AL Project | 2001 |
24 | Panzhihua Iron and Steel Co.,Ltd. | Power Plant Cool-rolled Chemical Water Station Anti-corrosion Project | 2001 |
25 | Mianning PKU Founder Tombarthite (New Material) Co.,Ltd. | Plant、Device and Sewage Treatment System Anti-corrosion Project | 2001 |
26 | Shuangliu Artificial Board( Guodong) | Plant Anti-corrosion & Insulation Project | 2002 |
27 | FAW (Sichuan) Special Cars Co.,Ltd. | Device Anti-corrosion Project | 2003 |
28 | BASF-YPC Co.,Ltd. | OXO and AA/AE Devices Anti-corrosion Project | 2003 |
29 | Petro China Tibet Marketing Company | Product Tank of 725 Oil Depot Anti-corrosion Project | 2004 |
30 | Xiluodu Hydroelectric Station | Water Pipe Anti-corrosion Project | 2004 |
31 | Lutianhua Group Co.,Ltd. | 400,000 Tons/ Year Methanol Device Anti-corrosion & Insulation Project | 2004 |
32 | Hainan Jianglin | Chlorine Pipe Anti-corrosion Project(100MTPD Caustic Soda Program) | 2004 |
33 | Hainan Jinhai Pulp & Paper Co., Ltd. | Sulfuric Acid Equipment Anti-corrosion Project | 2004 |
34 | Yuntianhua Co.,Ltd. | 20,000 Tons / Year polyformaldehyde Anti-corrosion & Insulation Project | 2004 |
35 | FAW (Sichuan) Special Cars Co.,Ltd. | Trench、Tank FRP Lining Anti-corrosion Project | 2004 |
36 | Yibin Haifeng Herui Co.,Ltd. | Yibing Haifeng Herui Co.,Ltd. Anti-corrosion & Insulation Project | 2007~2008 |
37 | Tibet Yulong Copper Industry Co.,Ltd. | FRPM & FRP Pipes Anti-corrosion Project | 2008 |
38 | Chengdu Yuanye Real Co.,Ltd. | Cooling Oil Waste Refining Device Anti-corrosion Project | 2009 |
39 | Yibin Haifeng Herui Co.,Ltd. | 1.2Million Tons / Year Cement (Carbide Slag Comprehensive Utilization) Anti-corrosion & Insulation Project | 2009 |
40 | Sichuan Pharmaceuticals Co.,Ltd. | Erythromycin Thiocyanate Extraction Apparatus FRP Anti-corrosion Project | 2009 |
41 | China Chengda Engineering Co.,Ltd. | VCM Device Anti-corrosion Project (Hanhua Chemical Industry (Ningbo) VCM/PVC) | 2010 |
42 | Chongqing Puyuan Chemical Industry Co.,Ltd. | Metatitanic Acid Device Rubber Lining Anti-corrosion Project | 2010 |
43 | Chongqing Puyuan Chemical Industry Co.,Ltd. | Titanium Dioxide Production Program Anti-corrosion Project | 2010 |
44 | Chengdu Bolei Resource Circulation Development Co.,Ltd. | Phase 1st Steel Tank Farm Anti-corrosion Project | 2010 |
45 | Chengdu Bolei Resource Circulation Development Co.,Ltd. | Device、Pipe and Steel Structure Anti-corrosion Project | 2011 |
46 | Yibing Haifeng Herui Co.,Ltd. | Anti-corrosion & Insulation Project(Phase 2nd Raise Investment Project) | 2011 |
47 | Yibing Haifeng Herui Co.,Ltd. | Thermal Power & Public Works Anti-corrosion & Insulation Project(Yibing Haifeng Herui Co.,Ltd. Phase 2nd Raise Investment Project) | 2011 |
48 | Shandong Hualu Hengsheng Group | Acetic Acid Plant Energy-saving Renovation Anti-corrosion Project | 2011 |
49 | Xinjiang Guanghui New Energy Co.,Ltd. | Concrete Bypass Flue Anti-corrosion Project (1.2Million Tons/ Year Methanol、800,000 Tons/ Year Dimethyl Ether Project) | 2011 |
50 | Inner Mongolia Kaiyuan Lvye Co.,Ltd. | Fly Ash Comprehensive Utilization Program Anti-corrosion Project | 2011 |
51 | Inner Mongolia Kaiyuan Lvye Co.,Ltd. | Fly Ash Comprehensive Utilization Program Tanks and Trench System Anti-corrosion Project | 2012 |
52 | Wuhan Kaidi | Biomass Power Generation Program 1×30MW Unit Plant Insulation Project | 2012 |
53 | Yunnan Xiangfeng Jinmai Chemical Co.,Ltd. | Accident Pool System Anti-corrosion Project | 2012 |
54 | Sichuan Auto Industry Co.,Ltd. | Pit & Trench Anti-corrosion Project | 2012 |
55 | Anhui Huainan Pingwei No.2 Power Plant | 3-4# Units Flue Gas Denitrification Project | 2012 |
56 | Chengdu Bolei Resource Circulation Development Co.,Ltd. | Ash Conveying Pipe & Pipe Gallery Anti-corrosion Project | 2012 |
57 | Yibin Haifeng Herui Co.,Ltd. | Hydrazine hydrate Program Anti-corrosion and Insulation Project | 2012 |
58 | Chongqing Puyuan Chemical Industry Co.,Ltd. | New Preparation Tanks Rubber Lining Anti-corrosion Project | 2013 |
59 | CPI Guizhou Jinyuan Group Co.,Ltd. Nayong Power Plant | Guizhou Nayong No.2 Power Plant 2# (4×300MW) Unit Denitration Project | 2013 |
60 | Formosa Industry Corporation Ningbo Branch | Formosa Ningbo Public Pipe Frame Anti-corrosion & Insulation Project | Under Construction |
61 | Xinjiang Jinhui Zhaofeng Energy Co.,Ltd. | Self-supply Power Station Phase 1st 2*350MW Unit FGD Project | Under Construction |
62 | Dongli Guangfu Electric Co.,Ltd. | Dongli 6000Tons Polysilicon Improvement Installment Project | Under Construction |
63 | Inner Mongolia Mengdong Energy Co., L td | Inner Mongolis Ewenke Power Plant 2*600MW Flue Gas SCR Denitration Project | Under Construction |
64 |
China National Chem.Engg.No.7 Construction Co.,Ltd. |
Headquarters Economy Building Water-proof Project(Anti-corrosion and Insulation) | Under Construction |
65 | CPI Xinjiang Energy Chemical Group Co.,Ltd. Wusu Thermal Power Branch | CPI Wusu Power Plant 2*330MW Unit Flue Gas Denitration Improvement Project | Under Construction |
66 | Yibin Haifeng Herui Power Plant Co.,Ltd | Yibin Haifeng Herui Power Plant Co.,Ltd(2014) Maintenance Project Contract | Under Construction |
Part of FGD Projects
No. | Power (Environmental Protection) Company | Project Name | Construction Time |
1 | China Huaneng Group | Chongqing Luohuang Power Plant Phase 1st、2nd 4×360MW 1-4# Units FGD Project | 1993-1998 |
2 | CPI Corporation | Chongqing Power Plant 2×200MW FGD Improvement Project | 1999 |
3 | China Datang Corporation | Guangdong Shajiao A Power Plant 5# Unit FGD Project | 2003 |
4 | Shandong Sanrong | Guizhou Anshun Power Plant 3-4# 2×300MW units FGD Project | 2003 |
5 | Shenzhen Energy Resource | Shenzhen Western Power Plant 5-6# 2×300MW Units FGD Project | 2003 |
6 | Shenzhen Energy Resource | Shenzhen Western Power Plant 3# 1×200MW Unit FGD Project | 2003 |
7 | Shenzhen Energy Resource | Shenzhen Mawan Power Plant 1-2# 2×300MW Units FGD Project | 2004 |
8 | CPI Corporation | Chongqing Jiulong Western Power Plant 1×220MW FGD Project | 2004 |
9 | China Huadian Corporation | Sichuan guang’an 2×300MW Unit FGD Project | 2004 |
10 | China Huadian Corporation | Guizhou Guiyang Power Plant 2×200MW FGD Project | 2004 |
11 | China Datang Corporation | Hebei Gaojing Power Plant 1-8# Units FGD Project | 2004~2006 |
12 | China Datang Corporation | Hebei Douhe Power Plant 1-8# 1×200 MW Units FGD Project | 2004~2009 |
13 | China Datang Corporation | Hebei Tangshan Power Plant 1-5# Units FGD Project | 2005 |
14 | China Datang Corporation | Anhui Huaibei Power Plant Phase 5 1*210MW Unit FGD Improvement Project | 2005 |
15 | China Datang Corporation | Guangdong Datang Chaozhou Sanbaimen Power Plant 1-2# Units FGD Project | 2005 |
16 | China Datang Corporation | Hebei Wangtan Power Plant 4×600MW Unit FGD Project | 2005 |
17 | China Datang Corporation | Jiangsu Xutang Power Plant 2×300MW Unit FGD Project | 2005 |
18 | CPI Corporation | Guizhou Guixi Power Plant 2×300MW Unit FGD Project | 2005 |
19 | CPI Corporation | Shanxi Hejin Power Plant Phase 1st 2×300MW Unit FGD Project | 2005 |
20 | CPI Corporation | Jiangsu Ligang Power Phase 2nd 2×350MW Unit FGD Project | 2005 |
21 | CPI Corporation | Henan Pingdingshan Power Plant 2×200MW Unit FGD Project | 2005 |
22 | CR Group | Jiangsu Changshu Power Plant 2×600 MW Unit FGD Project | 2005 |
23 | China Huaneng Group | Huaneng Beijing Thermal Power Plant Phase 1st 2X830t/h Boiler FGD Improvement Project | 2005 |
24 | China Huaneng Group | Hunan Huaneng Yueyang Power Plant Phase 2nd 2×300MW Unit FGD Project | 2005 |
25 | China Huaneng Group | Sichuan Huiying Power Plant 2×300MW Unit FGD Project | 2005 |
26 | Qingdao Power Plant | Shandong Qingdao Power Plant 1-2# Units FGD Project | 2005 |
27 | Insigma Group | Guangdong Shajiao A Power Plant 1-4# Units FGD Project | 2005 |
28 | Insigma Group | Guangxi Liuzhou Power Plant 2×200MW unit FGD Project | 2005 |
29 | Shenhua Group | Sichuan JIangyou Power Plant Phase 1st 2×300MW Unit FGD Project | 2005~2006 |
30 | China Datang Corporation | Inner Mongolia Touketuo Power Plant 8×600MW Unit FGD Project | 2005~2006 |
31 | Insigma Group | Guizhou Zunyi Power Plant 2×125MW unit FGD Project | 2006 |
32 | Wuhan Kaidi | Guangdong Zhujiang Power Plant Phase 2nd 30# 2×300MW Unit FGD Project | 2006 |
33 | Wuhan Kaidi | Chongqing Luohuang Power Plant Phase 3 2×600MW Unit FGD Extension Project | 2006 |
34 | China Datang Corporation | Henan Xinyang Power Plant 2×300 MW Unit FGD Project | 2006 |
35 | China Datang Corporation | Gaojing Power Plant 1-4# Coal-fired Units FGD Project | 2006 |
36 | China Datang Corporation | Zhejiang Wushashan 4×600MW Unit FGD Project | 2006 |
37 | China Datang Corporation | Shanxi Yungang Thermal Power Plant 2×300 MW Unit FGD Project | 2006 |
38 | China Datang Corporation | Guangdong Chaozhou Power Plant 2×600MW Unit FGD Project | 2006 |
39 | China Datang Corporation | Shandong Huangdao Power Plant Phase 3 Seawater FGD Anti-corrosion Project | 2006 |
40 | CPI Corporation | Henan Pingwei Power Plant 2×600MW Unit FGD Porject | 2006 |
41 | CPI Corporation | Chongqing Baihe Power Plant 2×300MW Unit FGD Porject | 2006 |
42 | CPI Corporation | Sichuan Douba Power Plant 2×100MW Unit FGD Porject | 2006 |
43 | CPI Corporation | Inner Mongolia Jinqiao Power Plant 2×300MW Unit FGD Porject | 2006 |
44 | CPI Corporation | Chongqing Hechuan Power Plant 2×300MW Unit FGD Porject | 2006 |
45 | CPI Corporation | Shanxi Yongji Power Plant 2×300MW Unit FGD Porject | 2006 |
46 | CPI Corporation | Zhejiang Yuhuan Power Plant 1-2# 4×1000MW Units FGD Porject | 2006 |
47 | CPI Corporation | Lingxia LIngwu Power Plant Phase 1st 2×600MW Unit FGD Porject | 2006 |
48 | CPI Corporation | Ningxia Malian Power Plant 2×330MW unit FGD Project | 2006 |
49 | CPI Corporation | Guangdong Zhuhai Power Plant Phase 1st 3-4# Units FGD Project | 2006 |
50 | China Huaneng Group | Shandong Huaneng Dezhou Power Plant 2×300MW Unit FGD Project | 2006 |
51 | China Huadian Corporation | Sichuan Huangjiaozhuang Power Plant 2×200MW Unit FGD Project | 2006 |
52 | China Huadian Corporation | Sichuan Neijiang Baima Power Plant 30# 2×200MW Unit FGD Project | 2006 |
53 | China Huadian Corporation | Neijiang Power Plant 21-22#(2X200MW) FGD Project | 2006 |
54 | China Guodian Corporation | Shiheng Power Plant Phase 2nd 2X300MW Coal-fired Unit FGD (EPC) Project | 2006 |
55 | Dongfang Boiler Group | Sichuan JIangyou Power Plant Phase 2nd 2×300MW Unit FGD Project | 2006 |
56 | Dongfang Boiler Group | Fujian Xiamen Songyu Power Plant 4×300MW Unit Seawater FGD Project | 2006 |
57 | Urban Environmental Protection | Nantong Meiya Thermal Power Plant (B) EPC Project | 2006 |
58 | Yibing Tianyuan | Yibing Haifeng Herui Co.,Ltd. Phase 1st Thermal Insulation Project | 2006 |
59 | China Datang Corporation | Henan Yichuan 1-2# Power Plant 2×125MW Units FGD Project | 2006~2007 |
60 | China Datang Corporation | Shanxi Hancheng Power Plant Phase 1-2 2×600 MW Units FGD Project | 2006~2008 |
61 | China Datang Corporation | Henan Datang Shouyangshan Power Plant 2×300 MW Unit FGD Project | 2007 |
62 | China Datang Corporation | Shanxi Yuncheng Power Plant 2×600MW Unit FGD Project | 2007 |
63 | China Datang Corporation | Shanxi Tongchuan Power Plant 2×600 MW Unit FGD Project | 2007 |
64 | China Datang Corporation | Henan Baoding Power Plant 2×200 MW Unit FGD Project | 2007 |
65 | CPI Corporation | Guangdong Yunfu Power Plant 1-4# Units FGD Project | 2007 |
66 | CPI Corporation | Guangdong Luoding Power Plant 2×135 MW Unit FGD Project | 2007 |
67 | CPI Corporation | Hebei Shijiazhuang Power Plant 12-15# Boiler Project | 2007 |
68 | CPI Corporation | Shanxi Hejin Phase 2nd 2×300MW Unit FGD Project | 2007 |
69 | CPI Corporation | Anhui Huainan Tianji Power Plant 2×600MW Unit FGD Project | 2007 |
70 | CPI Corporation | Henan Nanyang Power Plant Phase 1st 2×210MW Unit FGD Project | 2007 |
71 | CPI Corporation | Sichuan Jialing Power Plant 2×142MW Unit FGD Project | 2007 |
72 | CPI Corporation | Shanghai Waigaoqiao Power Plant 2×600 MW Unit FGD Project | 2007 |
73 | China Huadian Corporation | Shandong Huadian zhangqiu Power Plant 2×135MW Unit FGD Project | 2007 |
74 | Universtar Science & Technology (Shenzhen) Co.,Ltd. | Luoyang Yichuan Longquan Kengkou Self-generation Power Plant 2X300MW Unit FGD Project | 2007 |
75 | Shandong Luneng | Sichuan Baima Power Plant Phase 2nd 3# 1×200MW Unit FGD Project | 2007 |
76 | Chongqing Heyi | Luolan Graphite Industry (Chongqing) Co.,Ltd. FGD Project | 2007 |
77 | Mega-Green Environmental Science & Technology Co.,Ltd. | Henan Xin’an Power Plant 2×300 MW Unit FGD Project | 2007 |
78 | Wuhan Kaidi | Jiangsu Xinhai Power Plant 11-12# Units FGD Project | 2007 |
79 | Wuhan Kaidi | Inner Mongolia Wuhai Power Plant 2×300 MW Unit FGD Project | 2007 |
80 | Universtar Science & Technology (Shenzhen) Co.,Ltd. | Henan Yichuan No.3 Power Plant Phase 1st、2nd 2 FGD Project | 2007~2008 |
81 | Zijin Mining Group | Tibet Yulong Copper Industry Co.,Ltd. Phase 1st FRPM & FRP Pipes Anti-corrosion Project | 2007~2009 |
82 | China Datang Corporation | Jiangxi Datang Xinyu Power Plant 2×220MW Unit FGD Project | 2008 |
83 | China Datang Corporation | Huainan Tianjia’an Power Plant 5# Unit FGD Project | 2008 |
84 | CPI Corporation | Shanxi Weihe Power Plant 2×300 MW Unit FGD Project | 2008 |
85 | CPI Corporation | Shandong Liaocheng Power Plant 2×300 MW Unit FGD Project | 2008 |
86 | CPI Corporation | Hainan Haikou Power Plant Phase 2nd 2×125 MW Unit FGD Project | 2008 |
87 | CPI Corporation | Guizhou Qian’gui Power Plant Phase 1st 3# Unit FGD Project | 2008 |
88 | CPI Corporation | Hechuan Shuanghuai Power Plant Phase 1s 2×300MW Unit FGD Project | 2008 |
89 | CPI Corporation | Fushun Power Plant 1-2#(2X200MW)FGD Project | 2008 |
90 | China Huadian Corporation | Liaoning Tieling Power Plant 2×600 MW Unit FGD Project | 2008 |
91 | SinoEnv | Xinjiang Weihuliang Power Plant 2×600 MW Unit FGD Project | 2008 |
92 | Jiangnan Envirmental Protection | Guizhou Tianfu Chemical Co.,Ltd. 4×130t/hv Boiler FGD Project | 2008 |
93 | Jiangnan Envirmental Protection | Dezhou Thermal Power Plant 1-4#、7-9# Boilers FGD Project and 1-3# Thionizer Anti-corrosion Project | 2008 |
94 | Sigma Group | Ningxia Xixia Power Plant 2×200 MW Unit FGD Project | 2008 |
95 | Sigma Group | Shanxi Baoji No.2 Power Plant 4×300MW Unit FGD Project | 2008 |
96 | Wuhan Kaidi | Anhui Anqing Wanjiang Power Plant 2X300MW Unit FGD Project | 2008 |
97 | Wuhan Kaidi | Hefei Power Plant 5-6# (2X600MW)Units FGD Project | 2008 |
98 | CR Group | Guangzhou Huarui Thermal Power Plant Phase 2nd(2X330MW)Unit FGD Project | 2008 |
99 | China Datang Corporation | Datang Hancheng No.2 Power Plant Phase 2nd 1#、4# 2X600MW Units FGD Project | 2008~2012 |
100 | China Datang Corporation | Fushun Power Plant 1-2# 2×200MW Units FGD Project | 2009 |
101 | China Datang Corporation | Guangdong Datang Chaozhou 3-4# 2×1000MW Units FGD Project | 2009 |
102 | China Datang Corporation | Jiangsu Datang Lvsigang Power Plant Phase 1st 4×660MW Unit FGD Project | 2009 |
103 | China Datang Corporation | Gansu Datang Jingtai Phase 1st 2×660MW Unit Project | 2009 |
104 | CPI Corporation | Xinjiang Huadian Changji Thermal Power Plant Phase 2nd 2×125MW FGD Improvement Project | 2009 |
105 | CPI Corporation | Henan Pingdingshan No.2 Power Plant 2×1000MW FGD Project | 2009 |
106 | CPI Corporation | Jiangxi Xichang Power Plant 2×660MW Unit FGD Project | 2009 |
107 | CPI Corporation | Inner Mongolia Yuanbaoshan Power Plant 600MW Unit FGD Project | 2009 |
108 | Chaoyue Environmental Protection | Sichuan Dazhou Iron and Steel Group Sintering FGD Project | 2009 |
109 | Sigma Group | Guangdong Nanhai No.1 Power Plant 2×200MW Unit FGD Project | 2009 |
110 | Sigma Group | Yunnan Qujing Power Plant Unit 4×300MW Unit FGD Projec | 2009 |
111 | Wuhan Kaidi | Huaneng Yangluo Power Plant Phase 1st 2X300MW FGD Improvement Project | 2009 |
112 | Wuhan Kaidi | Qilu Petrochemical Thermal Power Plant 1-4# Furnaces FGD Project | 2009 |
113 | Wuhan Kaidi | Guangdong Nanhai No.1 Power Plant 2×300MW Unit FGD Project | 2009 |
114 | Wuhan Kaidi | Inner Mongolia Hailaer Thermal Power Plant Phase 3 2×200MW Unit FGD Project | 2009 |
115 | Wuhan Kaidi | Anhui Hefei No.2 Power Plant 2×350MW Coal-fired Unit FGD Project | 2009 |
116 | Wuhan Kaidi | Gansu Yongchang Power Plant 2×300MW Unit FGD Extension Project | 2009 |
117 | China Datang Corporation | Shanxi Datang Yungang Thermal Power Plant Phase 1st、2nd 4×300MW Units FGD Project | 2010 |
118 | China Datang Corporation | Shanxi Datang Linfen Hexi Thermal Power Plant 2×300MW Unit FGD Project | 2010 |
119 | CPI Corporation | Jilin Siping Power Plant 2×300MW Unit FGD Project | 2010 |
120 | CPI Corporation | Dalian Anjingzi Thermal Power Plant 2×300MW Unit FGD Project | 2010 |
121 | CPI Corporation | Hebei Liangchun Thermal Power Plant 2×300MW Unit FGD Project | 2010 |
122 | CPI Corporation | Huaneng Jinling Power Plant Phase 2nd 2×600MW Unit NO.2 Absorption Tower Anti-corrosion Project | 2010 |
123 | CPI Corporation | Jiangxi Guixi Power Plant FGD Project | 2010 |
124 | CPI Corporation | Jiling Baicheng Power Plant 2×600MW Unit FGD Project | 2010 |
125 | CPI Corporation | Wusu Thermal Power Plant Phase 1st 2×300MW Unit FGD Project | 2010 |
126 | CPI Corporation | Guizhou Yemazhai Power Plant 3×200MW FGD EPC Project | 2010 |
127 | CPI Corporation | Jiangxi Jingde Town Power Plant 2×600MW Unit FGD Project | 2010 |
128 | CPI Corporation | Ningxia Linhe Powerstation Phase 1st FGD Project | 2010 |
129 | CPI Corporation | Chongqing Yongchuan Power Plant 2×135MW Unit FGD Project | 2010 |
130 | Huadian Environmental Protection | Sichuan Gongxian Power Plant 2×600MW unit FGD Project | 2010 |
131 | Huaneng Zhongtai | Huaneng Tai’an Zhongtai Power Plant FGD Anti-corrosion Project | 2010 |
132 | Sigma Group | Nanhai Power Plant Phase 1st FGD Improvement Project | 2010 |
133 | China Huaneng Group | Huaneng Tongchuan Power Plant Phase 1st (2X600MW) 1-2# Coal-fired Units FGD Improvement Project | 2010~2011 |
134 | CR Group | Nanjing Huarun Thermal Power Plant 3-4# 330MW Units FGD Improvement Project | 2011 |
135 | Wuhan Kaidi | Xinjiang Akesu Thermal Power Plant 2×200MW FGD Project | 2011 |
136 | Wuhan Kaidi | E’zhou Power Plant Phase 2nd 2X600MW Unit FGD Improvement Project | 2011 |
137 | Wuhan Kaidi | Xinjiang Zhonghe 2×150MW CHP FGD Project | 2011 |
138 | Wuhan Kaidi | Sichuan Luzhou Chuannan Power Plant 2×600MW Unit Improvement Project | 2011 |
139 | Sigma Group | GD Power JIuquan Thermal Power Plant 2×330MW FGD (EPC) Project | 2011 |
140 | China Datang Corporation | Datang Hancheng No.2 Power Plant FGD Project | 2011 |
141 | China Datang Corporation | Guangdong Datang International Chaozhou Power Plant FGD Improvement Project | 2011 |
142 | CPI Corporation | Datang Hancheng No.2 Power Plant 1# FGD Project | 2011 |
143 | CPI Corporation | Wanzhou Salt Chemical Industry Park Heat Supply Center Phase 1st FGD Project | 2011 |
144 | CPI Corporation | CISC 1#360㎡Sintering Unit FGD Project | 2011 |
145 | China Huadian Corporation | Sichuan guang’an Phase 3 Gypsum Dehydration System FGD Project | 2011 |
146 | Kanglai Environmental Protection | Guangzhou Yuebao Cement Co.,Ltd. Urban Domestic Sewage Treatment Device Anti-corrosion | 2011 |
147 | Urban Environmental Protection | Pan’gang Xichang Vanadium-titanium Resource comprehensive utilization Program Sintering Phase 1st Project | 2011 |
148 | Shenchuan Environmental Protection | Xijiang Guanghui 1.2Million Tons/ Year Methanol、800,000 Tons/ Year dimethyl ether Project (FGD) | 2011 |
149 | Shenchuan Environmental Protection | Hubei Xiangyun Group 200,000 Tons、400,000Tons Vitriol Device FGD Project | 2011 |
150 | Shandong Hualu Hengsheng Group | Thermodynamic Ammonia FGD Improvement Project | 2011 |
151 | China Boqi | Huaneng Shanxi Qinling 2×600MW Air Cooling Coal-fired Unit FGD Project | 2011 |
152 | China Huaneng Group | Huaneng Luohua Power Plant Phase 1st 2*360MW FGD Anti-corrosion Project | 2011~2012 |
153 | CPI Corporation | Shanghai Changxingdao 2nd Power Plant 1-2# Boiler FGD Project | 2012 |
154 | CPI Corporation | Guizhou Xingyi Power Plant 2×600MW Units FGD Project | 2012 |
155 | CPI Corporation | Guizhou Xishui Power Plant 2# (4*135MW) Unit FGD Improvement Project | 2012 |
156 | Xinjiang Guanghui | 1.2 Million Tons/ Year Methyl Alcohol、800,000 Tons/ Year Dimethyl Ether Project | 2012 |
157 | Xinyuechao Environmental Protection | FUBangV-TI 180㎡ Sintering Machine FGD Project | 2013 |
158 | Xinyuechao Environmental Protection | Weiyuan Steel Co.,Ltd. Vanadium Resources Comprehensive Utilization Project Sintering System FGD Project | 2013 |
159 | Zhejiang Tianjing | SDIC Qujing Power co.,Ltd. 4×300MW Units BOT Project 2# Absorption Tower Ant-corrosion Engineering | 2013 |
160 | Zhejiang Atmosphere Environmental Protection Group | Guangxi Liuzhou Power Plant 2×220MW Units FGD Project | 2013 |
161 | CR Group | CR Power Hubei Co.,Ltd. Puyin Power Plant Phase2nd (2×1000MW) FGD Project | 2013 |
162 | China Datang Corporation | Datang Taiyuan 2nd Thermal Power Plant 9# FGD Improvement Project | 2013 |
163 | China Datang Corporation | Datang Baoding Thermal Power Plant FGD Anti-corrosion Project | 2013 |
164 | China Datang Corporation | Datang Hancheng 2nd Power Plant 1-4# Units FGD Project | 2013 |
165 | China Datang Corporation | Inner Mongolia Tuoketuo Power Plant FGD Project | 2013 |
166 | CPI Corporation | Chongqing Jiulong 7# Unit FGD Improvement Project | 2013 |
167 | CPI Corporation | Chongqing Hechuan Shuanghuai Power Plant phase 2nd Extension Project | 2013 |
168 | CPI Corporation | Shanxi Qingshui Power Plant 2*1000MW Unit FGD Project | 2013 |
169 | CPI Corporation | Ningxia Energy Linhe Power Plant 1# Flue Anti-corrosion Project | 2013 |
170 | CPI Corporation | Inner Mongolia Huomei Hongjun Company Self-supply Power Plant 3-6# Boilers FGD Project | 2013 |
171 | CPI Corporation | Guizhou Qianxi Power Plant 4*300MW units FGD Technology Improvement Project | 2013 |
172 | CPI Corporation | Jiangsu Kanshan Power Plant 1-2# units FGD Improvement Project | 2013 |
173 | China Huaneng Group | Huaneng Luohuang Power Plant 3-6# FGD Anti-corrosion Projec | 2013 |
174 | China Huaneng Group | Huaneng Yueyang Power Plant Phase 2nd 2*300MW FGD Improvement Project | 2013 |
175 | China Huaneng Group | Huaneng Shantou Power Plant Phase 1st 2*300 MW units FGD Improvement Project | 2013 |
176 | China Huaneng Group | Huaneng Tongchuan Power Plant 2# unit (1*600MW) FGD Project | 2013 |
177 | China Huaneng Group | Huaneng Huaiyin 2nd Power Plant 6# unit FGD Improvement Project | 2013 |
178 | Kaiyuan Lvye | Fly Ash Comprehensive Utilization FGD Project | 2013 |
179 | Shandong Hualu Hengsheng Group | Shandong Hualu Hengsheng Ammonium FGD Anti-corrosion Project (Acetic Acid New Energy-saving Technology Improvement Project) | 2013 |
180 | Shandong Hualu Hengsheng Group | Hualu Hengshen Large Melamine FGD Project | 2013 |
181 | Beijing SPC | Taishan Steel Group 265㎡Sintering FGD Project (Ironmaking technology Improvement Project ) | 2013 |
182 | Beijing SPC | Shenhua Shendong Electric Co.,Ltd. Diantadian Power Plant 2×660MW Thermal Power Unit FGD Project | 2013 |
183 | Wuhan Kaidi | Huaneng Yangluo Power Plant phase 2nd 2*300MW Unit FGD Improvement Project | 2013 |
184 | Wuhan Kaidi | Xinjiang Shenhuo 4*350 MW Power Station FGD EPC Project | 2013 |
185 | CPI Corporation | Shanxi Huadian Yuheng Coal & Electricity Co.,Ltd. phase 1st 2*600 MW FGD Project | 2013 |
186 | CPI Corporation | Shanxi Weihe Power Plant 3-4# units FGD Improvement Project | 2013 |
187 | CPI Corporation | Guizhou Jinyuan Group Nayong Power Plant 1-2# Units FGD Improvement Project | 2013 |
188 | CPI Corporation | CPI Yuanda Environmental Protection Co.,Ltd. Shanxi Shentou Power Plant 2*600MW FGD Project | 2013 |
189 | CPI Corporation | Guizhou Qianxi Zhongshui Power Plant 4*300 MW Unit FGD Improvement Project | 2013 |
190 | Xi’an Xire Boiler | Huaneng Huaiyin 2nd Power Plant 5# FGD Improvement Project | 2013 |
191 | China Huadian Corporation | Fujian Huadian Kemen Power Plant Phase 1 2*600MW unit Improvement Project | 2013 |
192 | CIP Corporation | Yuanbaoshan Power Plant 2*600MW Unit FGD Improvement EPC Project | 2014 |
193 | Beijing SPC | Gujiao Power Plant Phase 2nd 2×600MW Unit FGD System Improvement Project | 2014 |
194 | CPI Corporation | Shanxi Weihe Power Plant 4# Unit FGD Improvement Project2014 | 2014 |
195 | China National Chem.Engg.No.7 Construction Co., L td. | Pingwei Power Plant 3-4# Units DeNOx Project | 2013 |
196 | Wuhan Kaidi | Xinjiang Jinhui Self-generation Phase 1(2*350)unit FGD Project | 2014 |
197 | Wuhan Kaidi | Huaneng Yushe Power Plant 2×300MW Unit Improvement Project | 2014 |
198 | Zhejiang Atmosphere Environmental Protection Group | Guizhou Panxian Power Plant 1-2# Units (2*660MW) FGD Project | 2014 |
199 | Beijing SPC | Shenhua Jiangyou Power Plant 2*330MW Unit Technology Improvement Project | 2014 |
200 | Beijing SPC | Inner Mongolia JInlian Aluminum co., Ltd. 3 million Tons Aluminium Magnesium Alloy Project | Under Construction |
201 | Beijing SPC | Gujiao Phase 2 2*600MW Unit FGD Improvement Project | 2014 |
202 | Beijing SPC | Xinjiang Toumchouq 2×350MW FGD BOT Project | Under Construction |
203 | Beijing SPC | Douhe Power Plant(Datang International Power Generation Co.,Ltd.)3-8# Unit FGD Improvement Project | 2014 |
204 | Beijing SPC | Xiahuayuan Power Plant(Datang International Power Generation Co.,Ltd.) 3# Unit FGD System Improvement Project | 2014 |
205 | Beijing SPC | Datang Qian’an Thermal Power Plant 1# Unit FGD System Improvement Project | 2014 |
206 | Beijing SPC | Baotou Rare Earth Aluminium Industry Co., Ltd. 2# FGD System (4-6# Boilers) Improvement EPC Project | 2014 |
207 | Beijing SPC | Sichuan Bashu Jiangyou Power Plant 2×300MW unit FGD Technology Improvement Project | 2014 |
208 | CPI Corporation | Huaneng Yuhuan Power Plant Phase 2 Units FGD Improvement Project | 2014 |
209 | CPI Corporation | Henan Jiulong Kaifeng Branch 2×600MW Unit FGD Improvement Project | 2014 |
210 | CPI Corporation | JIulong Electric Power Guixi Branch 5-6# Units FGD Improvement Project | 2014 |
211 | CPI Corporation | Inner Mongolia Helinhe Self-supply Power Plant 2×350MW Unit FGD Extension Project | 2014 |
212 | CPI Corporation | Inner Mongolia Jinlian Aluminum co., Ltd. 3-6# Coal-fired Supercritical Unit FGD Project | Under Construction |
213 | CPI Corporation | Nanyang Yuanda Thermal Power Plant 2X210MW unit FGD Improvement Project | 2014 |
214 | CPI Corporation | Zhuhai Power Plant phase 1 3-4# Units FGD Improvement Project | 2014 |
215 | CPI Corporation | Pingdingshan 2X1000MW Unit FGD Improvement Project | 2014 |
216 | CPI Corporation | Jilin Songhuajiang 2XCB40MW+CB50MW Units FGD EPC Project | 2014 |
217 | CPI Corporation | Yaxi Power Plant 1-2# FGD & Sharing System Improvement Project | 2014 |
218 | CPI Corporation | Shanghai-Electric-Power Caojing Power (Shanghai) Co.,Ltd.2# Unit FGD Improvement EPC Project | 2014 |
219 | CPI Corporation | Henan Jiulong Xinxiang Branch 6# FGD System Improvement Project | 2014 |
220 | CPI Corporation | Huaneng Jinling Power Plant 2×1030MW Unit FGD System Improvement Project | Under Construction |
221 | China Huaneng Group | Inner Mengdian Huaneng Wuhai Power Plant 2×330MW Unit FGD Improvement Project | 2014 |
222 | China Huaneng Group | Huaneng Changxing Power Plant Wet FGD Project | 2014 |
223 | China Huaneng Group | Huaneng Luohuang Power Plant Phase 1 No.1 Unit FGD Project | 2014 |
224 | China Datang Corporation | Datang Shimen Power Plant 2×300MW Unit FGD Improvement Project | Under Construction |
225 | China Datang Corporation | Datang Changchun Power Plant 1-2# Units FGD Improvement Project | 2014 |
226 | China Datang Corporation | Tianjing Datang Power Plant 2X600MW Unit FGD Project | 2014 |
227 | China Datang Corporation | Ningxia Datang Power Plant 5-6# Units FGD Improvement Project | 2014 |
228 | East Hope Group | Baotou Rare Earth Aluminium Industry Co., Ltd 2*350MW No.8 Boiler FGD Project | 2014 |
229 | Shandong Hualu Hengsheng Group | Hualu Hengsheng 2-3# Units FGD Improvement Project | 2014 |
230 | Inner Mongolia Huaning Thermal Power Co.,Ltd. | Inner Mongolia Huaning Thermal Power Co.,Ltd. FGD Improvement Project | 2014 |
231 | Xiwang Group | Thermal Power Plant 1×220t/h Boiler FGD Project | Under Construction |
232 | Shenhua Guoneng Energy Group | Yuanyanghu Power Plant FGD Improvement Project | 2014 |
233 | Xi’an Xire Boiler | Inner Mongolia Shangdu Power Plant Phase 2nd 2×600MW Unit FGD Improvement Project | 2014 |
234 | Sichuan Guang’an Power Plant | 61# FGD System Lining Anti-corrosion Engineering | 2014 |
235 | Tongfang Environment Co.,Ltd. | Lingzhou Power Plant(Ninglu Coal Power Co.,Ltd.) 2×135MW CFB Boiler Unit FGD Improvement EPC Project | Under Construction |
236 | Beijing SPC | Inner Mongolia Jinlian Aluminum co., Ltd. 3-6# Coal-fired Supercritical Unit FGD Project | Under Construction |
237 | Beijing Noromo Energy Conservation and Environment Protection Technology Co.,Ltd. | Beipiao Power Co.,Ltd. 5×75t/h Boiler FGD Improvement Project | 2014 |
238 | Huaneng Chongqing Luohuang Power Co.,Ltd. | Huaneng Chongqing Luohuang Power Co.,Ltd.(2014)3-4# Units FGD System Glass Flake Anti-corrosion Engineering | 2014 |
239 | Huaneng Chongqing Luohuang Power Co.,Ltd. | Huaneng Chongqing Luohuang Power Co.,Ltd.5-6# Units FGD Spraying Layers (two) Glass Flake Anti-corrosion Engineering | 2014 |
240 | Huaneng Chongqing Luohuang Power Co.,Ltd. |
Huaneng Chongqing Luohuang Power Co.,Ltd. Phase 2nd FGD Demister Improvement Anti-corrosion Engineering
|
2014 |
241 | Huaneng Chongqing Luohuang Power Co.,Ltd. | Huaneng Chongqing Luohuang Power Co.,Ltd. PhaseⅡ、Ⅲ FGD Glass Flake Anti-corrosion Engineering | 2014 |
242 | CPI Corporation | Linhe Power Plant 1#-2# Units FGD Improvement Project | Under Construction |
243 | CPI Corporation | Xining Thermal Power Plant 2×660MW Supercritical Units FGD Project | Under Construction |
244 | CPI Corporation | Guizhou Nayong Horizontal Flue Plugging Anti-corrosion Project | 2014 |
245 | Chengdu Power Machinery Factory | Taizhou Power Plant Anti-corrosion Project | Under Construction |
246 | Shandong Hualu Hengsheng Group | Power Island FGD Glass Flake Anti-corrosion Project | 2014 |
247 | Beijing SPC | Tianjin SDIC Jinneng Electric Power Co.,Ltd.2×1000MW Units 1# Boiler FGD & WESP Improvement Project(FGD) | Under Construction |
248 | CPI Corporation | Wusitai Thermal Power Plant 2×300MW Units FGD Improvement EPC Project | Under Construction |
249 | Shandong Guoshun Group | Tianjin SDIC Jinneng Electric Power Co.,Ltd.2×1000MW Units 1# Boiler FGD & WESP Improvement Project(WESP) | Under Construction |
250 | CPI Corporation | Fenyi Power Plant 9# Boiler Wet FGD Device Installation Project | 2014 |
Chimney Anti-corrosion Projects
No. | Power Company & Owner | Project Name | Chimney Height(Meter) | Construction Time |
1 | China Power investment Corporation | Inner Mongolia Yuanbaoshan Power Plant NO.2 Chimney Project(Concrete) | 210 | 2009 |
2 | China Power investment Corporation | Inner Mongolia Yuanbaoshan Power Plant NO.1 Chimney Project(Concrete + Firebrick) | 180 | 2009 |
3 | Yibin Haifeng Herui Power Plant Co.,Ltd. | Yibin Haifeng Herui Cement Chimney Project(Steel Chimney) | 120 | 2009 |
4 | Yibin Haifeng Herui Power Plant Co.,Ltd. | Yibin Haifeng Herui Power Plant Chimney Project(Concrete) | 180 | 2010 |
5 | China Huadian Corporation | Huangjiaozhuang Power Plant Chimney Project(Concrete + Brick) | 240 | 2010 |
6 | China Huadian Corporation | Shenyang Tieling Power Plant 1# Chimney Project(Concrete + Brick) | 240 | 2010 |
7 | Chongqing Dalkia Co., Ltd | Chongqing Dalkia Power Plant Chimney Project(Concrete + Brick) | 180 | 2011 |
8 | Wuliangye Group | Workshop no.523 1# Chimney Improvement Project | 50 | 2011 |
9 | China Huadian Corporation | Sichuan Guang’an Power Plant phase 3 (2*600MW) chimney improvement project | 240 | 2011 |
10 | China Power investment Corporation | Chongqing Yongchuan Power Plant 2*135MW Unit Chimney Improvement Project | 180 | 2011 |
11 | Yunnan Yunjing Forestry & Pulp Co., Ltd. | Boiler Chimney Anti-corrosion Project | 180 | 2011 |
12 | China Huadian Corporation | Huangjiaozhuang Power Plant 2*200MW Unit Chimney Project | 240 | 2011 |
13 | China Power investment Corporation | Yongchuan Power Plant 1# Chimney Project | 180 | 2011 |
14 | China Power investment Corporation | Huadian Baiyinhua Power Plant Chimney Project | 210 | 2012 |
15 | China Power investment Corporation | Changxindao Power Plant Chimney Project | 180 | 2012 |
16 | China Guodian Corporation | Chengdu Jintang Power Plant Chimney Anti-corrosion Project | 210 | 2013 |
17 | Guizhou Jinchi Chemical Co.,Ltd. | Guizhou Jinchi Power Plant Chimney Anti-corrosion Project | 150 | 2013 |
18 | China Huadian Corporation | Sichuan Guang’an Power Plant Phase 2nd 2*600MW Unit Chimney Improvement Project | 240 | Under Construction |
Part of Installment Projects
No. | Owner & General Contractor | Project Name | Construction time |
1 | China National Chem.Engg.No.7 Construction Co., L td. | Pingwei Power Plant 3-4# Units DeNOx Project | 2013 |
2 | CPI Guizhou Jinyuan Group Co.,Ltd. Nayong Power Plant | Guizhou Nayong No.2 Power Plant 2# (4×300MW) Unit Denitration Project | 2013 |
3 | Formosa Industry Corporation Ningbo Branch | Formosa Ningbo Public Pipe Frame Anti-corrosion & Insulation Project | Under Construction |
4 | Xinjiang Jinhui Zhaofeng Energy Co.,Ltd. | Self-supply Power Station Phase 1st 2*350MW Unit FGD Project | Under Construction |
5 | Dongli Guangfu Electric Co.,Ltd. | Dongli 6000Tons Polysilicon Improvement Installment Project | Under Construction |
6 | China National Chem.Engg.No.7 Construction Co.,Ltd. | Headquarters Economy Building Water-proof Project(Anti-corrosion and Insulation) | Under Construction |
7 | CPI Xinjiang Energy Chemical Group Co.,Ltd. Wusu Thermal Power Branch | CPI Wusu Power Plant 2*330MW Unit Flue Gas Denitration Improvement Project | Under Construction |
8 | Inner Mongolia Mengdong Energy Co., L td | Inner Mongolis Ewenke Power Plant 2*600MW Flue Gas SCR Denitration Project | Under Construction |
9 | CPI Guizhou Jinyuan Group Co.,Ltd. Nayong Power Plant | Guizhou Nayong No.1 Power Plant 3# (4×300MW) Unit | Under Construction |